Prospectus Submitted for full SACSCOC Board approval

March 15 submission to SACSCOC Board of Trustees September 1 submission to SACSCOC Board of Trustees
   
April to Sept: Determine if request is a substantive change
(this could be UCC approval of a program or a new off-campus location)
December to March: Determine if request is a substantive
change (this could be UCC approval of a program or a new off-campus location)
October – December: Department works on draft of the prospectus March – May: Department works on draft of the prospectus
December 15: Prospectus submitted to Academic Affairs June 15: Prospectus submitted to Academic Affairs
January 30: Finalize Prospectus July 31: Finalize Prospectus
Spring Implementation Fall Implementation

 

Prospectus Submitted to Executive Council of SACSCOC for approval

January 1 submission to SACSCOC July 1 submission to SACSCOC
   

February to May: Determine if request is a substantive
change (this could be UCC approval of a program or a new
off-campus location)

September to January: Determine if request is a
substantive change (this could be UCC approval of
a program or a new off-campus location)
June to September: Begin working on the prospectus February to April: Begin working on the prospectus
October 1: Prospectus submitted to Academic Affairs May 1: Prospectus submitted to Academic Affairs
December 1: Submit Prospectus to SACSCOC June: Submit Prospectus to SACSCOC