SACSCOC Timeline
Prospectus Submitted for full SACSCOC Board approval
March 15 submission to SACSCOC Board of Trustees | September 1 submission to SACSCOC Board of Trustees |
April to Sept: Determine if request is a substantive change (this could be UCC approval of a program or a new off-campus location) |
December to March: Determine if request is a substantive change (this could be UCC approval of a program or a new off-campus location) |
October – December: Department works on draft of the prospectus | March – May: Department works on draft of the prospectus |
December 15: Prospectus submitted to Academic Affairs | June 15: Prospectus submitted to Academic Affairs |
January 30: Finalize Prospectus | July 31: Finalize Prospectus |
Spring Implementation | Fall Implementation |
Prospectus Submitted to Executive Council of SACSCOC for approval
January 1 submission to SACSCOC | July 1 submission to SACSCOC |
February to May: Determine if request is a substantive |
September to January: Determine if request is a substantive change (this could be UCC approval of a program or a new off-campus location) |
June to September: Begin working on the prospectus | February to April: Begin working on the prospectus |
October 1: Prospectus submitted to Academic Affairs | May 1: Prospectus submitted to Academic Affairs |
December 1: Submit Prospectus to SACSCOC | June: Submit Prospectus to SACSCOC |
Fall Implementation | Spring or Fall Implementation |